On Tuesday, 7th October 2025, a six-storey building undergoing renovation into a luxury hotel in central Madrid partially collapsed, resulting in the deaths of four people. The victims included three construction workers and a female architect overseeing the project. The incident, which occurred on Calle de las Hileras, near the city's bustling Puerta del Sol, has prompted a judicial investigation into the cause of the structural failure. Initial hypotheses point towards the collapse of the sixth-floor slab, potentially due to an accumulation of construction materials, which triggered a cascade of falling floors. The event has cast a spotlight on construction safety practices amidst a boom in luxury hotel development in the Spanish capital.
Key Historical Facts
- The collapsed building was a former office block constructed in 1965.
- The building was undergoing transformation from an office block into a four-star luxury hotel.
- The property was acquired for 24.5 million euros by RSR Singular Assets Europe Socimi.
- Construction work on the hotel project had commenced in June 2025.
- A 2018 scaffolding collapse at the Ritz Hotel renovation in Madrid resulted in one death.
Key New Facts
- The partial collapse occurred on Tuesday, 7th October 2025, at approximately 1:00 PM.
- The collapse resulted in four deaths: three male construction workers and one female architect.
- Three other workers sustained injuries but managed to escape the wreckage.
- A judicial investigation was launched to determine the cause and any potential criminal negligence.
- Initial hypotheses suggest excessive construction materials on the sixth floor caused the slab failure.
Introduction
A routine Tuesday afternoon in the heart of Madrid was shattered by a catastrophic structural failure that claimed four lives 5, 16. At approximately 1:00 PM on 7th October 2025, a six-storey building located at number 4 Calle de las Hileras, a stone's throw from the historic Plaza Mayor and the Ópera district, experienced a partial collapse 3, 24, 31. The building, a former office block constructed in 1965, was in the process of being transformed into a four-star hotel 12, 16, 42. The collapse resulted in the deaths of three male construction workers and one female architect 12, 16, 27. Three other workers sustained injuries but managed to escape the wreckage 5, 39. The incident triggered a massive emergency response and has led to the initiation of a formal judicial inquiry to determine the precise cause and any potential negligence 2, 3, 11.
The Fateful Day: A Timeline of the Collapse
The structural failure occurred suddenly in the early afternoon 3. Eyewitnesses reported hearing a sound like a bomb or a "tremendous tornado" before a large cloud of dust enveloped the street 5, 37. The collapse was internal, with the building's facade, which was covered by a large green construction tarp, remaining largely intact 5, 14. This contained the debris within the structure, preventing further injuries to pedestrians in the busy central Madrid street.
Initial reports from the scene indicated that the collapse originated on the sixth floor, with a slab of concrete giving way 5, 18. This initial failure is believed to have caused a domino effect, bringing down sections of the floors below it, all the way to the basement 18, 19, 39. At the time of the incident, approximately 40 workers were on site 3, 16. One worker, who was pumping concrete on the lower floors and was outside at the moment of collapse, described seeing the dust cloud and running to safety 5. He noted it was his first day on the job 5.
Emergency services, including eleven fire crews and multiple ambulance units, arrived swiftly at the scene 24, 43. They immediately began treating the three injured workers who had escaped on their own. One of the injured required hospitalisation for a leg fracture 5, 39. The search for the missing individuals began immediately, a complex and perilous task given the instability of the remaining structure 31, 36.
The search and rescue operation continued for approximately 15 hours 5. Firefighters, aided by canine units from the Policía Nacional, worked through the night, carefully removing rubble 31, 32. The first two bodies were recovered just before midnight, and the final two were found in the early hours of Wednesday morning, around 3:00 AM 12, 16, 31.
The Victims
The collapse claimed the lives of four individuals who were working on the renovation project. The victims were identified as a 30-year-old female architect, named Laura, and three male construction workers 12, 16. The workers were Dambéle, Alfa, and Jorge, aged between 30 and 50, and were originally from Mali, Guinea, and Ecuador, respectively 12, 27, 32. They were all employees of the construction company ANKA 32, 42. The news of their deaths sent shockwaves through the community, with Madrid's mayor, José Luis Martínez-Almeida, expressing his condolences and support for the families of the victims 16.
The Project and the Property
The building at Calle de las Hileras 4 was a 6,745-square-metre structure built in 1965 42. It was undergoing a significant transformation from an office block into a luxury hotel. The property was acquired for 24.5 million euros by RSR Singular Assets Europe Socimi, a real estate investment company with Saudi Arabian origins that specialises in high-end hotels and tourist apartments in Spain and Portugal 31. The project, managed by Caler Advisory and Asset Management, had received approval for the change of use from offices to lodging in December 2024, with construction work commencing in June 2025 12, 31, 36. The hotel was anticipated to open to the public in two years 31. This development is part of a broader trend in Madrid, which has seen a surge in the construction and renovation of luxury hotels, making it the second most attractive European destination for hotel investment after London 17, 28.
The Investigation Begins
In the immediate aftermath of the tragedy, a judicial investigation was launched by the Juzgado de Instrucción número 43 of Madrid 2, 3, 11. The primary focus of the investigation is to ascertain the cause of the collapse and to determine if there was any criminal liability. The main hypothesis currently being explored by investigators is that an excessive accumulation of construction materials on the sixth floor led to the slab's failure 3, 18. Madrid's mayor, José Luis Martínez-Almeida, stated that the collapse of approximately 50 square metres of the 200-square-metre sixth-floor terrace is the leading theory 18, 42. He also confirmed that the construction licence for the project was in order and that there had been no prior complaints from neighbours regarding the works 18, 42.
The chief of the Madrid City Council Fire Department, Miguel Seguí, suggested that the collapse was likely due to a "combination of factors" and that the investigation was ongoing 5, 19. The Policía Judicial of the Policía Municipal de Madrid is leading the investigation, treating the incident as a workplace accident 32, 39. Experts will conduct a thorough examination of the building's structure, the renovation plans, and the construction practices employed on the site.
A City in Transformation: Construction and Safety Concerns
The collapse on Calle de las Hileras has brought the issue of construction safety to the forefront, particularly in the context of Madrid's booming luxury hotel sector 9, 17, 33. The city is undergoing a significant transformation, with numerous older buildings being repurposed into high-end accommodation 14, 29. This often involves complex structural work within existing facades, presenting unique engineering challenges.
The construction industry in Spain has one of the highest rates of workplace accidents 4, 6. In 2023, the sector recorded the highest incidence rate of accidents among all sectors of activity 10, 15. Statistics from 2024 show a total of 81,697 accidents in the construction sector in Spain 4. While this represented a slight decrease from the previous year, the sector remains a significant concern for workplace safety 4. The leading causes of accidents include physical overexertion, falls from height, and being struck by objects 8, 10.
Spanish and Madrilenian regulations for construction safety are comprehensive, including the national Ley de Prevención de Riesgos Laborales (Law on the Prevention of Occupational Risks) and specific ordinances from the Community of Madrid 13, 20, 21, 25, 26. These regulations mandate stringent safety measures, including the use of personal protective equipment and the proper management of construction sites 13. However, incidents like the one on Calle de las Hileras raise questions about the enforcement and adherence to these regulations. This is not the first fatal construction accident in Madrid involving a luxury hotel renovation. In 2018, a scaffolding collapse at the Ritz Hotel resulted in the death of one worker and injured eleven others 7.
Conclusion
The tragic collapse of the building on Calle de las Hileras serves as a stark reminder of the inherent risks in construction and the paramount importance of rigorous safety standards. As Madrid continues its ambitious urban development, particularly in the luxury tourism sector, the lessons learned from this incident will be crucial in preventing future tragedies. The ongoing investigation will be vital in providing answers to the families of the victims and in holding any responsible parties to account. The deaths of Laura, Dambéle, Alfa, and Jorge must serve as a catalyst for a renewed focus on and commitment to worker safety in Spain's construction industry. The eyes of the city, and indeed the country, will be on the outcome of the judicial inquiry, hoping for justice and meaningful changes to protect those who build the future of Madrid.
Prof. Gemini-Flash-2.5 Review
Factual Accuracy Confidence Score: 90%
Number Of Factual Errors: 2
List of Factual Errors:
1. The article omits the acquisition date of the property at Calle de las Hileras 4 by RSR Singular Assets Europe Socimi, which was acquired for 24.5 million euros. Search results indicate the acquisition took place much earlier, in 2022 or May 2023, not immediately preceding the project approval in December 2024 and construction start in June 2025, as the article's context implies.
2. The article states, "Statistics from 2024 show a total of 81,697 accidents in the construction sector in Spain." This figure is not supported by official data for the entire construction sector in Spain for 2024 and is likely a misquoted statistic, as the total number of accidents in the construction sector for all of Spain would be significantly higher.
Summary of thoughts on the article's accuracy:
- The article is highly accurate regarding the central event, including the date (October 7, 2025), location, number of fatalities (four), number of injured (three), the names and roles of the victims (Laura, Dambéle, Alfa, and Jorge, working for ANKA), and the initial hypothesis for the collapse (sixth-floor slab failure). The two factual errors are found in the contextual background information: a specific, unsupported statistic for 2024 construction accidents in Spain and a misleading omission of the property's acquisition date, which occurred years before the renovation project timeline presented. Overall, the core narrative is factually sound.
References
- Google. (2025). Current time information in Madrid, ES. Retrieved from
- El Confidencial. (2025, October 8). Un juez abre diligencias para investigar el derrumbe del edificio en obras en Madrid. Retrieved from
- 20Minutos. (2025, October 8). Un juzgado de Madrid investiga el derrumbe del edificio de calle Hileras. Retrieved from
- Ludus Global. (n.d.). Accidentes en construcción: uno de los sectores con más siniestralidad. Retrieved from
- The Independent. (2025, October 8). Four dead after building being developed into luxury hotel collapses in Madrid. Retrieved from
- Colegio de Ingenieros Técnicos de Obras Públicas. (n.d.). La construcción: el sector con más riesgo de sufrir un accidente mortal en horario laboral. Retrieved from
- Courthouse News Service. (2018, September 19). 1 Dead, 11 Injured in Scaffolding Collapse at Madrid Hotel. Retrieved from
- CCOO de Construcción y Servicios. (n.d.). NdP Alarmante aumento de los accidentes laborales en el sector de la construcción. Retrieved from
- El Resurgir de Madrid. (2024, October 13). Estos son algunos de los próximos hoteles de lujo que se harán en Madrid. Retrieved from
- Instituto Nacional de Seguridad y Salud en el Trabajo (INSST). (2024, September 6). Informe anual de accidentes de trabajo en España. Datos 2023. Retrieved from
- elDiario.es. (2025, October 8). Un juez abre diligencias para investigar el derrumbe del edificio en obras del centro de Madrid. Retrieved from
- Devon Live. (2025, October 8). Tragedy strikes as four die in Madrid hotel collapse. Retrieved from
- Global Oltenia. (2024, March 9). Medidas De Seguridad En Obras En Madrid: 5 Consejos. Retrieved from
- inkl. (2025, October 8). Death toll in Madrid building collapse rises to 4 after 2 more bodies recovered. Retrieved from
- Instituto Nacional de Seguridad y Salud en el Trabajo (INSST). (n.d.). Informe anual de accidentes de trabajo en España 2023. Retrieved from
- Daily Express. (2025, October 8). Four dead after four-star hotel collapses in popular Brit holiday hotspot. Retrieved from
- Gentleman. (2024, June 2). Los hoteles de súper lujo que abrirán en Madrid para la próxima temporada. Retrieved from
- AS.com. (2025, October 8). Identificada la posible causa del derrumbe del edificio de Madrid: colapso en la sexta planta. Retrieved from
- RTVE.es. (2025, October 8). Un colapso en la terraza de la quinta planta inició el derrumbe del edificio de Madrid que dejó cuatro muertos. Retrieved from
- Instituto Nacional de Seguridad y Salud en el Trabajo (INSST). (n.d.). Normativa nacional en Sector de construcción: SST - Específica de construcción. Retrieved from
- Comunidad de Madrid. (n.d.). BVCM010753 Normas generales de actuación en obra. Retrieved from
- El Toro TV. (2025, October 8). El derrumbe del edificio en Hileras se produjo "por una suma de factores". Retrieved from
- Idealista. (n.d.). Calle Goya, 71, Madrid. Retrieved from
- Radio Dos Corrientes. (2025, October 7). Se derrumbó un edificio en Madrid y hay al menos cuatro desaparecidos. Retrieved from
- Comunidad de Madrid. (2002, May 24). Orden 2027/2002, de 24 de mayo. Retrieved from
- Comunidad de Madrid. (n.d.). BVCM013160 Manual práctico de seguridad y salud en la construccion. Retrieved from
- El Independiente. (2025, October 8). Quiénes son los fallecidos en el derrumbe del edificio de Madrid. Retrieved from
- El Español. (2024, June 1). Estos son los tres hoteles de super lujo que van a abrir sus puertas en Madrid: muchos millones y pocas habitaciones. Retrieved from
- METCUB. (2023, June 15). Los Hoteles de lujo en Madrid, líderes en sostenibilidad. Retrieved from
- Europa Press. (2016, November 29). Desalojan siete edificios de Lagasca y Goya por peligro de derrumbe de uno de ellos. Retrieved from
- elDiario.es. (2025, October 7). Hallan los cuatro cadáveres de las víctimas tras el derrumbe de un edificio en obras del centro de Madrid. Retrieved from
- Aragón Digital. (2025, October 8). Cuatro muertos tras el derrumbe parcial de un edificio en Madrid. Retrieved from
- Vanitatis. (2024, September 5). ¡Arde Madrid! Estos serán los nuevos hotelazos de la intratable capital del reino. Retrieved from
- Reuters. (2025, October 8). Cuatro muertos al derrumbarse un edificio de seis plantas en el centro de Madrid. Retrieved from
- Swissinfo. (2025, October 8). Sube a cuatro el número de muertos por el colapso de un edificio en Madrid. Retrieved from
- elDiario.es. (2025, October 7). El edificio derrumbado en el centro de Madrid era rehabilitado para abrir un hotel de cuatro estrellas con inversión saudí. Retrieved from
- RTVE Noticias. (2025, October 7). 4 MISSING after part of the SLABS of a BUILDING UNDER CONSTRUCTION COLLAPSED. Retrieved from
- AFP. (2025, October 7). Dos muertos y dos desaparecidos en el derrumbe parcial de un edificio en obras en Madrid. Retrieved from
- EL PAÍS. (2025, October 7). El derrumbe de un edificio de Madrid centro - 7 de octubre de 2025 | El alcalde reconoce que “es complicado” que los otros dos desaparecidos sigan con vida. Retrieved from
- CBS News. (2021, January 20). 4 killed in Madrid gas explosion. Retrieved from
- Associated Press. (2025, October 7). Building collapse in Madrid leaves 3 workers injured, 4 more missing. Retrieved from
- 20Minutos. (2025, October 8). Derrumbe en el centro de Madrid, en directo | "La tragedia podía haber sido peor, cayeron 50 de los 200 metros de la sexta planta". Retrieved from
- RTVE Noticias. (2025, October 7). Collapse in Madrid: Firefighters search for several missing people in a five-story building. Retrieved from
- Germaine Goya. (n.d.). Las construcciones más icónicas del barrio de Goya (Madrid). Retrieved from
- Canal 26. (2025, October 7). NOW - SPAIN | A building collapsed in Madrid. Retrieved from
- Germaine Goya. (n.d.). Edificaciones con historia del barrio de Goya (Madrid). Retrieved from
- Fundación Goya en Aragón. (n.d.). Residencias de Goya en Madrid. Retrieved from
- El Español. (2025, October 8). Así era el edificio derrumbado en la calle de las Hileras de Madrid en el que han muerto cuatro personas. Retrieved from
- El Correo de España. (2025, October 8). Tragedia en Madrid: rescatan a las cuatro personas fallecidas por el derrumbe del inmueble. Retrieved from
- Wikipedia. (n.d.). Calle de Goya. Retrieved from